Users should also be added to Email Lists Spreadsheet so Lori can input them into MailChimp. 

To do in SBS

  • Make sure a date is in the launch field
  • check Launched checklist
  • remaining scrum points should be 0
  • please clear the project caution and project warning fields (the yellow field)
  • project can be set to "Finished" 

To do in a Site

  • If there are multiple domain names, links between subsites need to be absolute URLS (the whole domain name), not relative
  • For Redesigns, update control panel icons to SVGs (only blocker is if the site is till on the moria server)
  • For Redesigns, check that administrators have access to redirects, user logs and quick galleries 

 

To do in Google Calendar

  • If a site is pay for, confirm via contract if they have 3 months of unlimited support before paid support begins. Then add a Paid Support Begins item to the Solutio B/S calendar with a notification for yourself 2-3 weeks prior to remind them via email that paid support will begin

 

 When notifying client of a site launch, it is courteous to also remind them that they can cancel website hosting services with existing providers when they are ready.